One of the responsibilities of the Scrum Master is to ensure that the Product Owner does not change the Acceptance Criteria of a committed User Story in the middle of a Sprint.
In this regard, which of the following statements about Acceptance Criteria is correct?
A . User Story Workshops are held as part of Sprint Review.
B . Acceptance Criteria provide the objectivity required for the User Story to be considered as Done or not Done.
C . The Scrum Master defines and communicates the Acceptance Criteria to the Scrum Team.
D . During the Sprint Retrospect Meeting, the Acceptance Criteria provide context for the Product Owner to decide if a User Story has been completed satisfactorily.
Answer: B
Explanation:
Reference: https://blog.teamtreehouse.com/when-is-a-user-story-done-acceptance-criteria-definition-done