In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer.

Posted by: Pdfprep Category: C_ACTIVATE12 Tags: , ,

In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer.
A . Scheduling project plan
B . Final testing
C . Interface setup
D . Hyper care support

Answer: B