In the Define Activities process, the schedule management plan is used to:

In the Define Activities process, the schedule management plan is used to:
A .  Capture the lessons learned from other projects for comparison.
B .  Contain the standard activity list.
C .  Document and support the project change requests.
D .  Prescribe the level of detail needed to manage the work.

Answer: D