In SAP S/4HANA, how can you ensure that the system determines a suitable source of supply for a material during material requirements planning (MRP)? There are 3 correct answers to this question.
A . Create a valid scheduling agreement
B . Create a quota arrangement for the material
C . Create a purchasing info record with the Regular Supplier indicator set
D . Create a valid source list entry with the Fixed Supply Source indicator set
E . Create a purchasing info record with the Automatic Sourcing indicator set
Answer: A,B,E