Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: December 9, 2020 Pdfprep2020-12-09T12:56:45+00:00 In project management, a temporary project can be:A . Completed without planningB . Aroutine business processC . Long in durationD . Ongoing to produce goods View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.