PdfPrep.com

In Agile risk management, a risk burndown chart is best used to:

In Agile risk management, a risk burndown chart is best used to:
A . Qualitatively analyze the probability of a risk occurring.
B . Track progress on risk reduction of technical risks.
C . Document the external risks that could impact the project.
D . Illustrate the project risk profile and new and changing risks.

Answer: D

Exit mobile version