In a project, total float measures the:
A . Ability to shuffle schedule activities to lessen the duration of the project.
B . Amount of time an activity can be extended or delayed without altering the project finish date.
C . Cost expended to restore order to the project schedule after crashing the schedule.
D . Estimate of the total resources needed for the project after performing a forward pass.
Answer: B