In a project, total float measures the:

In a project, total float measures the:
A .  Ability to shuffle schedule activities to lessen the duration of the project.
B .  Amount of time an activity can be extended or delayed without altering the project finish date.
C .  Cost expended to restore order to the project schedule after crashing the schedule.
D .  Estimate of the total resources needed for the project after performing a forward pass.

Answer: B