If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?

The following chart lists stories for a release of an Agile project:

If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
A . 3
B . 4
C . 5
D . 7

Answer: B