If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team’s velocity?

Following chart lists stories for a release of an Agile project;

If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team’s velocity?
A . 9
B . 10
C . 12
D . 15

Answer: A