If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A .  Checkpoint Report
B .  Highlight Report
C .  Issue Report
D .  Product Status Account

Answer: C