PdfPrep.com

If people other than the Project Board members were doing Project Assurance, who would they report to?

If people other than the Project Board members were doing Project Assurance, who would they report to?
A . Corporate or programme management
B . The Project Board member overseeing the relevant area of interest
C . The Project Manager
D . The Team Manager whose Work Package execution is being monitored

Answer: B