If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?
A . The project should continue until the next end stage assessment
B . A benefits review should be undertaken
C . The project should be stopped or changed
D . An exception assessment should be held to approve an Exception Plan to recover from the situation
Answer: C