Posted by: Pdfprep
Post Date: November 16, 2020
If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that’s been made?
A . Checkpoint Report
B . Stage Plan
C . Benefits Review Plan
D . Project Plan
Answer: B