PdfPrep.com

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
A . .99
B . -$2,500
C . $2,500
D . 1.02

Answer: C

Exit mobile version