Identify the missing word(s) in the following sentence… The [?] is used by the Project Manager to capture and maintain information on all of the identified threats and opportunities relating to the project.
A . Risk Register
B . Risk Management Strategy
C . Issue Register
D . Risk owner
Answer: A