Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.
How should you address this?
A . Complete incomplete Stories
B . Increase or re-estimate Velocity
C . Re-estimate all small Stories
D . Switch to using Ideal days
Answer: A