During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer.
How should the team resolve this?
A . Refer to the values of the agile framework and the team
B . Review the signed customer contract
C . Check the sprint priority list
D . Submit the problem to the product owner
Answer: A