Component project managers create project management plans for all component projects in a program . The program manager notices that some project managers prefer one status report template, while others prefer another.
How should the program manager decide which template is appropriate?
A . Review the issue with the program management office (PMO) to determine which template to use.
B . Review the issue with the project managers and come to mutual agreement on which template to use.
C . Meet with the program governance board to select an appropriate template.
D . Allow the component project managers to use their preferred templates.
Answer: B