How should the business analyst (BA) handle the situation?

A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort.

How should the business analyst (BA) handle the situation?
A . Ask the project sponsor for additional funding
B . Escalate the request to the project manager for reevaluation of the plan
C . Spend the required effort to develop the detail
D . Explain that the degree of effort may not be necessary at this stage

Answer: B