An administrator needs to forecast infrastructure requirements for a new program and its associated applications. Prior to the projected start of the new program, all existing applications will be decommissioned.
How should the administrator perform this task?
A . Check the Disregard Existing Workloads radio button in the Runway scenario.
B . Check the Disregard Existing Nodes radio button in the Runway scenario.
C . Add up the recovered workloads and manually remove from the Runway configuration.
D . Power down the workloads during a maintenance window and run the Capacity Runway.
Answer: A