How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?

How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?
A . Maximum of one day for Sprints that are time-boxed to two weeks.
B . None. A new Sprint starts immediately following the conclusion of the previous Sprint.
C . Enough time for the last Increment to finish testing.
D . Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
E . All of the above are allowed.

Answer: B