How is the risk progress report used in the ‘implement’ step?
A . Identify the status against the activity’s stated measures for risk management
B . Identify the scales used to measure the probability and impact of a risk
C . Describe actions to enhance how risk management is performed
D . Gain agreement for the amount of risk that can be taken
Answer: A