Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?
A . By the planning time fence from the material master
B . By the firming mechanism with the longer firming interval
C . By the manual firming date
D . It is predefined in Customizing.
Answer: B