PdfPrep.com

How do you correct this?

An approved work order has been assigned an incorrect job plan.

How do you correct this?
A . Change the Job Plan Revision to the correct revision.
B . Clear the Job Plan field and enter the correct job plan.
C . Create a Follow-up work order with the correct job plan.
D . Select Remove Work Plan from the More Actions menu and enter the correct job plan.

Answer: D