A project administrator wants to give only read access to an SCM component to two separate teams.
How can this be done?
A . Assign read only access to the component.
B . Assign the component ownership to both teams.
C . Change the Access Control of the component to the project area.
D . Create an Access Group with both teams and assign read only permissions for the component to the Access Group.
Answer: B