How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
A . Collect stakeholder requirements
B . Conduct an iteration planning meeting
C . Communicate product backlog items to the stakeholders
D . Facilitate a product development roadmap workshop

Answer: A