How are asynchronous update requests of SAP transactions assigned to work processes of type Update V1 or Update V2? There are 2 correct answers to this question.
A . If V2 update work processes are not configured, V1 work processes handle all update requests.
B . If V2 update processes are configured, V2 update requests will only be processed in available V2 update work processes.
C . The processing priority for V1 and V2 update requests is determined by the corresponding value of the parameters rdisp/wp_no_vb and rdisp/wp_no_vb2.
D . All update requests are assigned to V1 and V2 work processes in a round-robin fashion.
Answer: A,B