During which process does the project team receive bids and proposals?

Posted by: Pdfprep Category: CAPM Tags: , ,

During which process does the project team receive bids and proposals?
A . Conduct Procurements
B . Plan Procurements
C . Estimate Costs
D . Control Budget

Answer: A

Explanation:

Process: 12.2 Conduct Procurements

Definition: The process of obtaining seller responses,

selecting a seller, and awarding a contract.

Key Benefit : The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements.