During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
A . Monitor and Control Project Work
B . Perform Quality Assurance
C . Close Project or Phase
D . Control Scope

Answer: C

Explanation:

Process: 4.6. Close Project or Phase

Definition: The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.

Key Benefit: The key benefit of this process is that it provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors. 