Posted by: Pdfprep
Post Date: March 16, 2021
In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
A . Program benefits and all component project activities
B . Component resources and their activity assignment/responsibility metrics
C . Program-level activities and integrated component projects
D . Program activities, component activities, and all other work
Answer: D
Leave a Reply