Posted by: Pdfprep
Post Date: June 23, 2021
During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project’s scope.
The business analyst (BA) facilitating the workshop should:
A . note the issue in the Issue Register to be considered by the Project Manager.
B . ignore the stakeholder’s comment and proceed with the agenda.
C . consider the issue’s impact on the project and gain agreement with stakeholders on the next step.
D . request the stakeholder to explain the issue further so that possible solutions can be discussed.
Answer: C