Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:
A . follow the change process flow and notify the legal department after the change is implemented.
B . extend a formal invitation to the legal department representative to join the CC
D . hold a separate meeting with the legal department representative and ask for approval.
E . notify the legal department representative in the event of an upcoming audit.
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294