Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
A .  project documents updates.
B .  project management plan updates.
C .  change requests.
D .  work performance information.

Answer: D