PdfPrep.com

CORRECT TEXT

CORRECT TEXT

A project manager is calculating the budget cost of a single project task called "Server Configuration".

This task is estimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.

One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.

Calculate the total budget cost for the task (ignoring any other resources or costs) – assuming a five day working week.

Give your answer as a whole number.

The total cost is $ .

Answer: 40800

Exit mobile version