Posted by: Pdfprep
Post Date: March 6, 2021
CORRECT TEXT
Refer to the exhibit.
Patchit Limited operates a job costing system. They have been asked to quote for a rush job that will require to be done in overtime hours.
It is estimated that the job will incur the following costs:
Production overheads are absorbed on a direct labour hour basis. Budgeted direct labour hours for the year were 50,000 and budgeted direct labour cost was $300,000.
If production overheads had been based on a percentage of direct labour cost, the revised production costs for the job would be:
Answer: $8