Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?
A . A self-organizing approach to increase team focus and maximize collaboration.
B . A virtual team to minimize feeling of isolation and gaps on sharing knowledge.
C . A distributed team to improve tracking progress, productivity, and performance.
D . A norming approach that requires team members to adjust their behavior and work together.
Answer: A