Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A . Enterprise environmental factors
B . Work performance reports
C . Organizational process assets
D . Context diagrams

Answer: A

Explanation: