Change requests are processed for review and disposition according to which process?

Posted by: Pdfprep Category: CAPM Tags: , ,

Change requests are processed for review and disposition according to which process?
A . Control Quality
B . Control Scope
C . Monitor and Control Project Work
D . Perform Integrated Change Control

Answer: D

Explanation:

Process: 4.5 Perform Integrated Change Control

Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.

Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs

Leave a Reply

Your email address will not be published.