PdfPrep.com

Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?

Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?
A . In traditional project management, once the user clarifies their quality expectations, it is the Project Manager who defines those user expectations in measurable terms.
B . In traditional project management, changes can be made only through a formal change management system.
C . In Scrum, the Scrum Master and the Scrum Team collaborate and decide on the Acceptance Criteria for the User Stories.
D . In Scrum, the development of the product is carried out by the Scrum Team in short iterations called Sprints.

Answer: C

Explanation:

Reference: https://www.scrum.org/index.php/forum/scrum-forum/29049/product-owners-define-acceptancecriteria-

then-refuse-it

Exit mobile version