A program is near completion and the benefits will be delivered shortly . The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?
A . Review the benefits management plan with the program sponsor
B . Obtain approval from the sponsor to close the program
C . Prepare performance evaluations for all program personnel
D . Prepare performance evaluations for all project personnel
Answer: B