Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

A . The iteration is in jeopardy.
B . The team has removed scope.
C . The iteration is ahead of schedule.
D . The team’s velocity is constant.

Answer: C