PdfPrep.com

Based on the chart, what is the cost variance (CV) for Task 6?

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
A .  -2,000
B .  0
C .  1,000
D .  2,000

Answer: D

Exit mobile version