Based on the chart, what is the cost performance index (CPI) for Task 2?

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?
A .  0.8
B .  1
C .  1.25
D .  1.8

Answer: C