What should be considered when configuring high availability and disaster recovery scenarios for
availability of Business Processes managed by Blue Prism? (Select 2)
A . Resource pools and Active Queues can be used to distribute work to Runtime Resources which are
online
B . The Runtime Resources are “stateful” devices, therefore any failure or maintenance event should also
be taken into account in the process design and scheduling methodology
C . Using a load balancer and 2 application servers will ensure high availability of an automated process
D . Use the setting within a Blue Prism Process to force a process to fail over to an alternative Runtime
Resource in the event of a failure.
Answer: AC