At the start of a typical project life cycle, costs are:

At the start of a typical project life cycle, costs are:
A .  low, peak as work is carried out, and drop as the project nears the end.
B .  low, become steady as work is carried out, and increase as the project nears the end.
C .  high, drop as work is carried out, and increase as the project nears the end.
D .  high, become low as work is carried out, and drop as the project nears the end.

Answer: D