Posted by: Pdfprep
Post Date: November 14, 2020
At the start of a typical project life cycle, costs are:
A . low, peak as work is carried out, and drop as the project nears the end.
B . low, become steady as work is carried out, and increase as the project nears the end.
C . high, drop as work is carried out, and increase as the project nears the end.
D . high, become low as work is carried out, and drop as the project nears the end.
Answer: D
Leave a Reply