As a Scrum Master how will you coordinate with the Product Owner to ensure Value-Driven Delivery on Scrum projects?
A . By ensuring that requirements are prioritized based on opportunity for investment
B . By ensuring that customers realize the value at the end of project
C . By ensuring that requirements are reprioritized after every Sprint
D . By understanding what adds value to customers and ensuing that stakeholders are closely involved throughout the project
Answer: D
Explanation:
In order to provide Value-driven Delivery, it is important to meet a few requirements. First, those involved in a project should understand what adds value to customers and users, and should prioritize the high value requirements in the Prioritized Product Backlog. Second, those involved in a project should decrease uncertainty and constantly address risks that can potentially decrease value if they materialize; it is important to show product increments to project stakeholders at the end of each Sprint, enabling effective management of changes. Third, those involved in a project should create deliverables by producing potentially shippable, value-based product increments during each Sprint so that customers start realizing value early in the project.
Reference: http://blog.scrumstudy.com/scrum-delivers-value-driven-delivery/