As a Scrum Master how will you coordinate with the Product Owner to ensure Value-Driven Delivery on Scrum projects?
A . By ensuring that requirements are prioritized based on opportunity for investment
B . By ensuring that customers realize the value at the end of project
C . By ensuring that requirements are reprioritized after every Sprint
D . By understanding what adds value to customers and ensuing that stakeholders are
closely involved throughout the project
Answer: D