Analyzing activity sequences, durations, resource requirements, and schedule constraints for project and monitoring and controlling relates to which process?

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project and monitoring and controlling relates to which process?
A . Develop Schedule
B . Control Schedule
C . Estimate Activity Durations
D . Define Activities

Answer: A

Explanation:

Reference: http://www.mypmps.net/en/mypmps/knowledgeareas/time/schedule-development.html