Analyzing activity sequences, durations, resource requirements, and schedule constraints for project and monitoring and controlling relates to which process?

Posted by: Pdfprep Category: CAPM Tags: , ,

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project and monitoring and controlling relates to which process?
A . Develop Schedule
B . Control Schedule
C . Estimate Activity Durations
D . Define Activities

Answer: A

Explanation:

Reference: http://www.mypmps.net/en/mypmps/knowledgeareas/time/schedule-development.html